ITM.KIBTEK14: ISKELE SUBSTATION PROJECT

A new 132kV substation was built in the Iskele region. Two 132/23.02kV 20/62.5MVA power transformers were supplied and installed, and the project has been completed.

Start: March 2023 – Completion: October 2024

Client: Cyprus Turkish Electricity Authority (KIB-TEK)