ITM.KIBTEK16: POWER TRANSFORMER SUPPLY AND INSTALLATION PROJECT

Within the scope of this project, two power transformers were supplied and installed.

Lefkoşa Substation: Supply and installation of one 132/11kV 62.5MVA power transformer.

Gönyeli MV Substation: Supply and installation of one 22/11kV 25MVA MIDEL oil-filled power transformer.

Start: November 2023 – Completion: December 2024

Client: Cyprus Turkish Electricity Authority (KIB-TEK)