ITM.KIBTEK18: YENİBOĞAZİÇİ SUBSTATION PROJECT
Yeniboğaziçi Substation: Construction of a new medium voltage metal clad building, supply and installation of MV switchgear, and supply and installation of one 132/11kV 50MVA and one 132/22kV 62.5MVA power transformer. A total of 4 new feeder bays.
Geçitkale Substation: Supply and installation of 3 feeder bays; transportation and installation of one 132/22kV 25MVA power transformer.
Kalecik Substation: Replacement of a high voltage circuit breaker.
Start: July 2025 – Planned Completion: November 2026
Client: Cyprus Turkish Electricity Authority (KIB-TEK)